ECONOMIC HIGHLIGHTS OF CPW PROJECT
Capacity 5 M.T./DAY

BASIS:

A.	No. of working days				: 300 per year
B.	No. of shifts					: 3, batch timing 22 Hrs.
C.	Plant capacity					: 5.00 MT / batch i.e. 1635 MT / year
D.	Chlorination					: 58-60
Production envisaged per annum: a. CPW : 1500 MT b. Hcl : 2700 MT FIXED COST: (Rs. In lacs) 1. LAND: 2000 sq. meters @ 100/-per sq.meters 2.00 2. BUILDING: 5.00 a. Plant does not require any building. b. Building for godown, office, chlorine shed Boundary wall, laboratory, electric room, Security office etc. 3. PLANT & MACHINERY: a. Main Plant (As per offer) 20.99 b. Other items 10.26 c. Erection 1.20 d. Excise duty, on 21.00 @ 13% 2.73 e. Sales tax, packing, forwarding, 1.87 transit, insurance etc. 6% on 31.25 37.05 4. OTHER ASSETS: a. Furniture & office equipment 0.30 b. Preliminary & Pre-operative exp. 1.00 d. Others 0.50 5. TOTAL FIXED COST:- 1. Land 2.00 2. Building & other civil work 5.00 3. Plant & machinery 37.05 4. Others 1.80 45.85 6. TOTAL PROJECT COST: A. Fixed cost 45.85 B. Margin for working capital 8.68 54.53 7. SOURCE OF FUNDS: a. Own capital 9.93 b. Term loan from financial corporation Land 2.00 Buildings 5.00 P & M 37.05 75% 33.00 c. Subsidy @ 15% 06.60 d. Unsecured loan 05.00 54.53 8. COST OF PRODUCTION PER ANNUM: A. RAW MATERIAL: S.No. Item Qty Rate / MT Amount in Lacs 1 HNP 630 0.25 157.50 2 Chlorine 1970 0.05 98.50 3 Hydrated lime 56 0.02 1.12 4 Stabilizer 6 0.68 4.08 Total 261.20 B. PACKING PVC Drum of 250 Kgs Cap. 6000 400/- 24.00 C. OTHER EXPENSES a. Salaries & wages 4.80 b. Repair & maintenance 0.72 c. Power, water & utilities 1.80 d. Insurance, rates, legal 0.84 e. Postage, Telephone etc. 0.84 f. Office expenses 0.84 g. Traveling Exp. 1.20 h. Conveyance and maintenance 1.20 i. Misc. exp. 1.20 13.44 D. INTEREST:- a. Term loan Rs. 33.00 @ 18% 5.94 b. On working capital loan on 4.94 21.00 @ 19% c. Unsecured loan on Rs. 05.00 @ 18% 0.90 11.78 E. DEPRECIATION: a. Building Rs. 05.00 lacs @5% 0.25 b. P & M Rs. 37.05 lacs @ 20% 7.41 c. Other assets Rs. 3.34 lacs @10% 0.34 8.00 TOTAL COST OF PRODUCTION 318.42 9. SALES REALISATION: 1. CPW 1500 MT @ 21500/- 322.50 2. Hcl 2700 MT @ 1500/- 40.50 363.00 10. PROFITABILITY: 1. Total cost of production 318.42 2. Sales realization: 363.00 44.58 11/ WORKING CAPITAL: S.No. Item Period Margin Amount Bank Margin 1 Raw Material ½ month 25% 10.88 8.16 2.72 2 Packing material ½ month 25% 1.00 0.75 0.25 3 Work in process 1 day 25% 0.70 0.52 0.18 (R.M. Cost basis) 4 Finished goods ¼ month 25% 6.80 5.10 1.70 5 Sundry debtors ½ month 25% 15.30 11.47 3.83 (selling price) Total 34.68 26.00 8.68